08th of March 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.
07th of March 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.
04th of March 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.
03rd of March 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.
02nd of March 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.
01st of March 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.
•28th of February 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.
•25th of February 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.
•24th of February 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.
•23th of February 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.
•22th of February 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.
•21th of February 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.
•18th of February 2010
Block Work & plaster work & MEP work Is in Progress.
•17th of February 2010
Block Work & plaster work & MEP work Is in Progress.
•16th of February 2010
Block Work & plaster work & MEP work & Fire rated door installation Is in Progress
•15th of February 2010
Block Work & plaster work & MEP work & Fire rated door installation Is in Progress
•14th of February 2010
Block Work & plaster work & MEP work & Fire rated door installation Is in Progress
•09th of February 2010
Block Work & plaster work & MEP work & Fire rated door installation Is in Progress.
•08th of February 2010
Block Work & plaster work & MEP work & Fire rated door installation at 12th floor Is in Progress.
•07th of February 2010
Block Work & plaster work & MEP work & Fire rated door installation at 12th floor Is in Progress.
•04th of February 2010
Block Work & plaster work & MEP work & Fire rated door installation at 12th floor Is in Progress.
•03rd of February 2010
Block Work & plaster work & MEP work & Fire rated door installation at 12th floor Is in Progress.
•02nd of February 2010
Block Work & plaster work & MEP work & Fire rated door installation at 11th floor Is in Progress.
•01st of February 2010
Block Work & plaster work & MEP work & Fire rated door installation at 10th floor Is in Progress.
•31st of January 2010
Ground Floor Block Work & plaster work & MEP work & Fire rated door installation at 10th floor Is in Progress.
•28th of January 2010
Ground Floor Block Work & plaster work & MEP work & Fire rated door installation at 10th floor Is in Progress.
•27th of January 2010
Ground Floor Block Work & plaster work & MEP work & Fire rated door installation at 10th floor Is in Progress.
•26th of January 2010
Ground Floor Block Work & plaster work & MEP work & Fire rated door installation at 10th floor Is in Progress.
•25th of January 2010
Ground Floor Block Work & plaster work & MEP work Is in Progress.
•24th of January 2010
Ground Floor Block Work & plaster work & MEP work & Stair case work GF. to FF Is in Progress& Fair Fighting pump has arrived to the wind site.
•21th of January 2010
Ground Floor Block Work & plaster work & MEP work & Stair case work GF. to FF Is in Progress.
•20th of January 2010
Ground Floor Block Work & plaster work & MEP work Is in Progress.
•19th of January 2010
Ground Floor Block Work & plaster work & MEP work Is in Progress.
•18th of January 2010
Ground Floor Block Work & plaster work & MEP work Is in Progress Also today second part of Elevators and Equipments has arrived in the Wind sites which are been unloading right now.
•17th of January 2010
Ground Floor Block Work Is in Progress &. The Fire Fighting pump has arrived in Jebel Ali Port and in one or two days will be release from the Port Authority and after the release it will go to the Wind Sites.After the Fire Fighting Pumps has been installed we will going to get COC III permit ,the last 2/3 slabs work progress has been done by undertaking letter.In Wind 1 slab has been inspecteded by Jafza and ready for casting and We waiting for COC III inspection. Also today Elevators and Equipments has arrived in the Wind sites which are been unloading right now
•14th of January 2010
Ground Floor Block Work Is in Progress.
•13th of January 2010
Ground Floor Block Work Is in Progress.
•12th of January 2010
Ground Floor Block Work Is in Progress.
•11th of January 2010
Ground Floor Block Work Is in Progress.
•10th of January 2010
Ground Floor Block Work Is in Progress.
•7th of January 2010
Ground Floor Block Work Is in Progress.
•23th of December 2009
Top bar installation & ssk work & mep work is in progress at level 24.
•22th of December 2009
Top bar installation & ssk work & mep work is in progress at level 24.
•21th of December 2009
Top bar installation & ssk work & mep work is in progress at level 24.
•20th of December 2009
Top bar installation & ssk work & mep work is in progress at level 24.
•17th of December 2009
Top bar installation & ssk work & mep work is in progress at level 24.
•15th of December 2009
Top bar installation & ssk work & mep work is in progress at level 24.
•14th of December 2009
Top bar installation & ssk work & mep work is in progress at level 24 & wind material is received
•12th of December 2009
Top bar installation & ssk work & mep work is in progress at level 24 & wind material is received.
•10th of December 2009
Top bar installation & ssk work & mep work is in progress at level 24 & wind material is received.
•9th of December 2009
Top bar installation & ssk work & mep work is in progress at level 24.
•8th of December 2009
Top bar installation & ssk work & mep work is in progress at level 24.
•7th of December 2009
Top bar installation & ssk work & mep work is in progress at level 24.
•6th of December 2009
Temporary Fire Fitting I& postention work is in progress at level 24.
•1st of December 2009
Mep work & steel fixing & postention work is in progress.
•30th of November 2009
Mep work & steel fixing & postention work is in progress.
•29th of November 2009
Mep work & steel fixing & postention work is in progress.
•25th of November 2009
Steel Fixing & MEP Work at t level 24(+60.37) is in Progress.
•19th of November 2009
Steel Fixing & MEP Work at t level 24(+60.37) is in Progress.
•18th of November 2009
Steel Fixing & MEP Work & SSK work at t level 24(+60.37) is in Progress.
•15th of November 2009
Beam installation at level 24(+60.37) is in Progress.
•12th of November 2009
Beam installation at level 24(+60.37) is in Progress.
•11th of November 2009
Beam installation at level 24(+60.37) is in Progress.
•10th of November 2009
Beam installation at level 24(+60.37) is in Progress.
•8th of November 2009
Beam installation at Level 24(+60.37) is in Progress.
•2nd of November 2009
Doka System Installation at Level 24(+60.37) is in Progress.
•1st of November 2009
Doka System Installation at Level 24(+60.37) is in Progress.
•29th of October 2009
Doka System Installation at Level 24(+60.37) is in Progress.
•28th of October 2009
Doka system installation at Level 24(+60.37) & Core wall De Shuttering at Level 23 (+59.40) to Level 24(+60.37 is in Progress.
•27th of October 2009
Doka system installation at Level 24(+60.37) & Core wall De Shuttering at Level 23 (+59.40) to Level 24(+60.37 is in Progress.
•26th of October 2009
Doka system installation at Level 24(+60.37) is in Progress & Core Wall Casting Will be done at 10 pm.
•25th of October 2009
Doka system installation at Level 24(+60.37) is in Progress.
•22th of October 2009
Slab Form Work at Level 24(+60.37) is in Progress.
•21th of October 2009
Core wall Shuttering at Level 23 (+59.40) to Level 24(+60.37) is in Progress.
•20th of October 2009
Core wall Shuttering at Level 23 (+59.40) to Level 24(+60.37) is in Progress.
•19th of October 2009
Core wall Shuttering at Level 23 (+59.40) to Level 24(+60.37) is in Progress.
•18th of October 2009
Core wall Shuttering at Level 23 (+59.40) to Level 24(+60.37) is in Progress.
•15th of October 2009
Column De Shuttering at Level 23 (+59.40) to Level 24 (+60.37) & Core wall Installation at Level 23 (+59.40) to Level 24(+60.37) is in Progress.
•14th of October 2009
Column Casting at Level 23 (+59.40) to Level 24 (+60.37) & Core wall Installation at Level 23 (+59.40) to Level 24(+60.37) is in Progress.
•13th of October 2009
Column Shuttering at Level 23 (+59.40) to Level 24 (+60.37) & Core wall Installation at Level 23 (+59.40) to Level 24(+60.37) is in Progress.
•12th of October 2009
Column Shuttering at Level 23 (+59.40) to Level 24 (+60.37) & Core wall Installation at Level 23 (+59.40) to Level 24(+60.37) is in Progress.
•11th of October 2009
Column Installation & Shuttering at Level 23 (+59.40) to Level 24 (+60.37) & Temporary Fire Alarm & Fire Fitting Installation is in Progress.
•08th of October 2009
Column Installation & Shuttering at Level 23 (+59.40) to Level 24 (+60.37) & Temporary Fire Alarm & Fire Fitting Installation is in Progress.
•07th of October 2009
Curing at Level 23 (+59.40) & Column Installation & Shuttering at Level 23 (+59.40) to Level 24 (+60.37) & Temporary Fire Alarm & Fire Fitting Installation is in Progress.
•06th of October 2009
Curing at Level 23 (+59.40) & Column Installation & Shuttering at Level 23 (+59.40) to Level 24 (+60.37) & Temporary Fire Alarm & Fire Fitting Installation is in Progress.
•04th of October 2009
Casting & Curing at Level 23 (+59.40) & Temporary Fire Fitting & Fire Alarm Installation is in Progress.
•01th of Octo.ber 2009
Column Pre Fabrication Level 23 (+59.40) to Level 24 (+60.37)& Temporary Fire Fitting & Fire Alarm Installation is in Progress.
•30th of September 2009
Top Mesh Installation& MEP Work at Level 23 (+59.40) & temporary fire rated door installation is in Progress.
•29 th of September 2009
Top Mesh Installation& MEP Work at Level 23 (+59.40) & temporary fire rated door installation is in Progress.
•28 th of September 2009
Top Mesh Installation& MEP Work at Level 23 (+59.40) & temporary fire rated door installation is in Progress.
•27 th of September 2009
Top Mesh Installation& MEP Work at Level 23 (+59.40) & temporary fire rated door installation is in Progress.
•24 th of September 2009
Top Mesh Installation& MEP Work at Level 23 (+59.40) & temporary fire rated door installation is in Progress.
•23 th of September 2009
Top Mesh Installation& MEP Work at Level 23 (+59.40) & temporary fire rated door installation is in Progress.
•22 th of September 2009
Bottom Mesh Installation& MEP Work at Level 23 (+59.40) & temporary fire rated door installation is in Progress.
•19 th of September 2009
Steel fixing & MEP Work at Level 23 / temporary fire rated door installation is in Progress.
•29 th of August 2009
Core wall Shuttering & Column Installation from Level 22 to Level 23 (+56.39 to +59.40) & Slab Removing from Level 21 to Level 23 (+53.38 to +59.40) & Temporary Fire Rated Door Installation Is in Progress.
•27 th of August 2009
Core wall Shuttering from Level 22 to Level 23 (+56.39 to +59.40) & Slab Removing from Level 21 to Level 23 (+53.38 to +59.40) & Temporary Fire Rated Door Installation Is in Progress.
•23 th of August 2009
Column Casting from Level 22 to Level 23 (+56.39 to +59.40) & Temporary Fire Rated Door Installation Is in Progress.
•20 th of August 2009
Curing at Level 22 (+56.39) & Column Shuttering from Level 22 to 23 (+56.39 to +59.40) & Temporary Fire Rated Door Installation Is in Progress.
•19 th of August 2009
Curing at Level 22 (+56.39) & Column Shuttering from Level 22 to 23 (+56.39 to +59.40) & Temporary Fire Rated Door Installation Is in Progress.
•18 th of August 2009
Curing at Level 22 (+56.39) & Core Wall Installation from Level 22 to 23 (+56.39 to +59.40) & Temporary Fire Rated Door Installation Is in Progress.
•17 th of August 2009
Curing at Level 22 (+56.39) & Column Installation from Level 22 to Level 23 (+56.39 to +59.40) & Core Wall Installation from Level 22 to 23 (+56.39 to +59.40) & Temporary Fire Rated Door Installation Is in Progress.
•16 th of August 2009
Curing at Level 22 (+56.39) & Column Installation from Level 22 to Level 23 (+56.39 to +59.40) & Core Wall Installation from Level 22 to 23 (+56.39 to +59.40) & Temporary Fire Rated Door Installation Is in Progress.
•14 th of August 2009
Casting & Curing at Level 22 (+56.39) & Temporary Fire Rated Door Installation Is in Progress.
•13 th of August 2009
Steel fixing & MEP Work at Level 22 (+56.39) & Column Installation from Level 22 to Level 23 (+56.39 to +59.40) & Temporary Fire Rated Door Installation Is in Progress & Slab 15th Casting Will be done to night.
•12 th of August 2009
Steel fixing & MEP Work at Level 22 (+56.39) & Column Installation from Level 22 to Level 23 (+56.39 to +59.40) & Temporary Fire Rated Door Installation Is in Progress.
•11 th of August 2009
Steel fixing & MEP Work at Level 22 (+56.39) & Column Installation from Level 22 to Level 23 (+56.39 to +59.40) & Temporary Fire Rated Door Installation Is in Progress.
•10 th of August 2009
Steel fixing & MEP Work at Level 22 (+56.39) & Column Installation from Level 22 to Level 23 (+56.39 to +59.40) & Temporary Fire Rated Door Installation Is in Progress.
•09 th of August 2009
Steel fixing at Level 22 (+56.39) & Temporary Fire Rated Door Installation Is in Progress.
•06 th of August 2009
Slab Fixing & Beam Installation at Level 22 (+56.39) & Temporary Fire Rated Door Installation Is in Progress.
•05 th of August 2009
Slab Fixing & Beam Installation at Level 22 (+56.39) & Temporary Fire Rated Door Installation Is in Progress.
•04 th of August 2009
Slab Fixing at Level 22 (+56.39) & Temporary Fire Rated Door Installation Is in Progress.
•03 rd of August 2009
Slab Fixing at Level 22 (+56.39) & Temporary Fire Rated Door Installation Is in Progress.
•02 nd of August 2009
Slab Fixing at Level 22 (+56.39) & Temporary Fire Rated Door Installation Is in Progress.
•30 th of July 2009
Slab Removing at Level 20 to Level 22 (+50.37 to+56.39) & Temporary Fire Rated Door Installation Is in Progress.
•29 th of July 2009
Slab Removing at Level 20 to Level 22 (+50.37 to+56.39) & Temporary Fire Rated Door Installation Is in Progress.
•28 th of July 2009
Core Wall De Shuttering at Level 21 to Level 22 (+53.38 to +56.39) & Slab Removing at Level 20 to Level 22 (+50.37 to+56.39) & Temporary Fire Rated Door Installation Is in Progress.
•27 th of July 2009
Column De Shuttering at Level 21 to Level 22 (+53.38 to +56.39) & Core Wall Shuttering at Level 21 to Level 22 (+53.38 to +56.39)& Temporary Fire Rated Door Installation Is in Progress & Core Wall Casting Will be Done Tonight.
•26 th of July 2009
Column De Shuttering at Level 21 to Level 22 (+53.38 to +56.39) & Core Wall Shuttering at Level 21 to Level 22 (+53.38 to +56.39)& Temporary Fire Rated Door Installation Is in Progress.
•23 th of July 2009
Column Shuttering at Level 21 to Level 22 (+53.38 to +56.39) & Core Wall Installation at Level 21 to Level 22 (+53.38 to +56.39) & Curing at Level 21 & Temporary Fire Rated Door Installation Is in Progress & Column Casting will be done Tonight.
•22 th of July 2009
Column Shuttering at Level 21 to Level 22 (+53.38 to +56.39) & Core Wall Installation at Level 21 to Level 22 (+53.38 to +56.39) & Curing at Level 21 & Temporary Fire Rated Door Installation Is in Progress.
•21 th of July 2009
Column Installation & Shuttering at Level 21 to Level 22 (+53.38 to +56.39) & Curing at Level 21 & Temporary Fire Rated Door Installation & Is in Progress.
•20 th of July 2009
Column Installation at Level 21 to Level 22 (+53.38 to +56.39) & Curing at Level 21 & Temporary Fire Rated Door Installation & Is in Progress.
•17 th of July 2009
Casting & Curing at Level 21 (+53.38) & Temporary Fire Rated Door Installation Is in Progress.
•16 th of July 2009
Top Bar Steel Fixing at Level 21 (+53.38) & Temporary Fire Rated Door Installation Is in Progress & Ready to Casting.
•15 th of July 2009
Top Bar Steel Fixing at Level 21 (+53.38) & Temporary Fire Rated Door Installation Is in Progress.
•14 th of July 2009
MEP Work & SSK Work & Top Bar Steel Fixing at Level 21 (+53.38) & Temporary Fire Rated Door Installation Is in Progress.
•13 th of July 2009
MEP Work & SSK Work & Top Bar Steel Fixing at Level 21 (+53.38) & Temporary Fire Rated Door Installation Is in Progress.
•12 th of July 2009
MEP Work & Bottom Mesh Steel Fixing at Level 21 (+53.38) & Temporary Fire Rated Door Installation Is in Progress.
•09 th of July 2009
MEP Work & Bottom Mesh Steel Fixing at Level 21 (+53.38) & Temporary Fire Rated Door Installation Is in Progress
•08 th of July 2009
MEP Work & Bottom Mesh Steel Fixing at Level 21 (+53.38) & Temporary Fire Rated Door Installation & Core Wall De Shuttering Level 20 to Level 21 (+50.37 to +53.38) Is in Progress.
•07 th of July 2009
MEP Work & Bottom Mesh Steel Fixing at Level 21 (+53.38) & Temporary Fire Rated Door Installation Is in Progress & Core Wall Shuttering Level 20 to Level 21 (+50.37 to +53.38) Is Finished & Ready for Casting.
•06 th of July 2009
Slab Fixing & MEP Work & Bottom Mesh Steel Fixing at Level 21 (+53.38) & Core Wall Shuttering Level 20 to Level 21 (+50.37 to +53.38) Temporary Fire Rated Door Installation Is in Progress.
•05 th of July 2009
Slab Removing from Level 19 to Level 21 (+47.36 to +53.38) & Slab Fixing at Level 21 & Core Wall Shuttering Level 20 to Level 21 (+50.37 to +53.38) Temporary Fire Rated Door Installation Is in Progress.
•02 nd of July 2009
Slab Removing from Level 19 to Level 21 (+47.36 to +53.38) & Temporary Fire Rated Door Installation Is in Progress
•01 st of July 2009
Slab Removing from Level 19 to Level 21 (+47.36 to +53.38) & Column De Shuttering at Level 20 to Level 21 (+50.37 to+53.38) & Temporary Fire Rated Door Installation Is in Progress.
• 30 th of June 2009
Curing at Level 20 (+50.37) & Core Wall Steel Fixing at Level 20 to Level 21 (+50.37 to+53.38) & Column De Shuttering at Level 20 to Level 21 (+50.37 to+53.38) & Temporary Fire Rated Door Installation Is in Progress.
• 29 th of June 2009
Curing at Level 20 (+50.37) & Core Wall Steel Fixing at Level 20 to Level 21 (+50.37 to+53.38) & Column Shuttering at Level 20 to Level 21 (+50.37 to+53.38) & Temporary Fire Rated Door Installation Is in Progress & Column Casting Will Be Done Tonight.
• 28 th of June 2009
Curing at Level 20(+50.37) & Core Wall Steel Fixing at Level 20 to Level 21 (+50.37 to+53.38) & Column Shuttering at Level 20 to Level 21 (+50.37 to+53.38) & Temporary Fire Rated Door Installation Is in Progress.
• 26 th of June 2009
Casting at Level 20(+50.37)
• 25 th of June 2009
Top Mesh Installation & Post Tension Work & MEP Work at Level 20(+50.37) Is Finished & Ready to Casting & Temporary Fire Rated Door Installation Is in Progress
• 24 th of June 2009
Top Mesh Installation & Post Tension Work & MEP Work at Level 20(+50.37) & Temporary Fire Rated Door Installation Is in Progress.
• 23 th of June 2009
Post Tension Work & MEP Work at Level 20 (+50.37) & Temporary Fire Rated Door Installation Is in Progress.
• 22 th of June 2009
Bottom Mesh Installation & MEP Work at Level 20 (+50.37) & Temporary Fire Rated Door Installation Is in Progress & Column Installation at Level 19 to Level 20 (+47.36 to+50.37) Is Finished.
• 21 th of June 2009
Slab Fixing & Bottom Mesh Installation & MEP Work at Level 20 (+50.37) & Temporary Fire Rated Door Installation & Column Installation at Level 19 to Level 20 (+47.36 to+50.37) Is in Progress.
• 18 th of June 2009
Slab Removing at Level 18 to Level 20 (+44.35 to +50.37) & Temporary Fire Rated Door Installation & Core Wall De Shuttering at Level 19 to Level 20 (+47.36 to+50.37) Is in Progress.
• 17 th of June 2009
Slab Removing at Level 18 to Level 20 (+44.35 to +50.37) & Temporary Fire Rated Door Installation Is in Progress , Core Wall Shuttering at Level 19 to Level 20 (+47.36 to+50.37) Is Finished Core wall Casting Will Be Done at 5 O'clock.
• 16 th of June 2009
Slab Removing at Level 18 to Level 20 (+44.35 to +50.37) & Temporary Fire Rated Door Installation Is in Progress.
• 15 th of June 2009
Curing at Level 19 (+47.36) & Core Wall Shuttering at Level 19 to Level 20 (+47.36 to +50.37) & Slab Removing at Level 18 to Level 20 (+44.35 to+50.37) & Temporary Fire Rated Door Installation Is in Progress.
• 14 th of June 2009
Curing at Level 19 (+47.36) & Slab Removing at Level 18 to Level 20 (+44.35 to+50.37) & Temporary Fire Rated Door Installation Is in Progress.
• 11 th of June 2009
Curing at Level 19 (+47.36) & Core Wall Shuttering at Level 19 to Level 20 (+47.36 to +50.37) & Column De Shuttering at Level 19 to Level 20 (+47.36 to +50.37) & Temporary Fire Rated Door Installation Is in Progress.
• 10 th of June 2009
Curing at Level 19 (+47.36) & Core Wall Installation at Level 19 to Level 20 (+47.36 to+50.37) & Column Shuttering at Level 19 to Level 20 (+47.36 to+50.37) & Temporary Fire Rated Door Installation Is in Progress.
• 09th of June 2009
Casting at Level 19 (+47.36) Is Finished & Curing at Level 19 (+47.36) & Core Wall Installation at Level 19 to Level 20 (+47.36 to+50.37) & Temporary Fire Rated Door Installation Is in Progress.
• 08th of June 2009
Cleaning of Slab at Level 19 (+47.56) & Ready to Casting & Core Wall Installation at Level 19 to Level 20 (+47.56 to+50.57) & Temporary Fire Rated Door Installation Is in Progress.
• 07th of June 2009
Steel Fixing at Level 19 (+47.56) & Core Wall Installation at Level 19 to Level 20 (+47.56 to+50.57) & Temporary Fire Rated Door Installation Is in Progress.
• 04th of June 2009
Steel Fixing & Post Tension Work at Level 19 (+47.56) & Core Wall Installation at Level 19 to Level 20 (+47.56 to+50.57) Is in Progress.
• 03rd of June 2009
Steel Fixing & Post Tension Work at Level 19 (+47.56) & Column & Core Wall Installation at Level 19 to Level 20 (+47.56 to+50.57) Is in Progress.
• 02nd of June 2009
Steel Fixing & Post Tension Work & MEP Work at Level 19 (+47.56) & Column Installation at Level 19 to Level 20 (+47.56 to+50.57) Is in Progress.
• 01st of June 2009
Steel Fixing & Post Tension Work & MEP Work at Level 19 (+47.56) & Column Installation at Level 19 to Level 20 (+47.56 to+50.57) Is in Progress.
• 31th of May 2009
Bottom Mesh Steel Fixing & Post Tension Work & MEP Work at Level 19 (+47.56) & Column Installation at Level 19 to Level 20 (+47.56 to+50.57) Is in Progress.
• 28th of May 2009
Slab Leveling & MEP marking at Level 19 (+47.56) Is in Progress.
• 27th of May 2009
Form Work Of Slab at Level 19 (+47.56) Is in Progress.
• 26th of May 2009
Form Work Of Slab at Level 19 (+47.56) Is in Progress.
• 25th of May 2009
Core Wall Casting & De Shuttering at Level 18 to level 19 (+44.35 to +47.56) & Form Work Of Slab at Level 19 (+47.56) Is in Progress.
• 24th of May 2009
Core Wall Shuttering at Level 18 to level 19 (+44.35 to +47.56) Is Finished & Ready for Casting & Form Work Of Slab at Level 19 (+47.56) Is in Progress
• 21th of May 2009
Core Wall Shuttering at Level 18 to level 19 (+44.35 to +47.56) & Form Work Of Slab at Level 19 (+47.56) Is in Progress.
• 20th of May 2009
Core Wall Shuttering at Level 18 to level 19 (+44.35 to +47.56) Is in Progress.
• 19th of May 2009
Column De Shuttering at Level 18 to level 19 (+44.35 to +47.56) & Aluminum Cladding & Glazing Sample installation Is in Progress.
• 18th of May 2009
Column Shuttering at Level 18 to level 19 (+44.35 to +47.56) &
Core Wall Installation at Level 18 to level 19 (+44.35 to +47.56) is finished & Columns Are Ready for the Casting.
• 17th of May 2009
Column Shuttering at Level 18 to level 19 (+44.35 to +47.56) & Core Wall Installation at Level 18 to level 19 (+44.35 to +47.56) is in Progress.
• 14th of May 2009
Casting & Curing at Level 18 (11th floor +44.35 )
• 13th of May 2009
Top Bar Steel Fixing & MEP Work is in progress & Post Tension Work at Level 18 (11th floor +44.35 ) & 11th floor is Ready for Casting.
• 12th of May 2009
Top Bar Steel Fixing & MEP Work is in progress & Post Tension Work at Level 18 (11th floor +44.35 ) & Column Installation at Level 18 to level 19 (+44.35 to +47.56) is Finished.
• 11th of May 2009
Bottom Mesh Steel Fixing & MEP Work & Post Tension Work at Level 18 (11th floor +44.35 ) & Column Installation at Level 18 to level 19 (+44.35 to +47.56) is in progress.
• 10th of May 2009
Slab Form Work Leveling & Bottom Mesh Steel Fixing & MEP Work & Post Tension Work at Level 18 (11th floor +44.35 ) & Column Installation at Level 18 to level 19 (+44.35 to +47.56) is in progress.
• 07th of May 2009
Slab Form Work at Level 18 (11th floor +44.35 ) & Column Installation at Level 18 to level 19 (+44.35 to +47.56) is in progress.
• 06th of May 2009
Slab Form Work at Level 18 (11th floor +44.35 ) is in progress.
• 05th of May 2009
Slab Form Work at Level 18 (11th floor +44.35 ) & Core wall De shuttering at Level 18 to level 19 (+44.35 to +47.56) is in progress.
• 04th of May 2009
Slab Form work at Level +44.35 (Level 18th, 11th Floor) & Core wall Shuttering & Casting at Level +41.34 to Level +44.35 is in Progress.
• 03rd of May 2009
Slab Form work at Level +44.35 (Level 18th, 11th Floor) & Core wall Shuttering at Level +41.34 to Level +44.35 is in Progress.
• 30th of April 2009
Slab Form work at Level +44.35 (Level 18th, 11th Floor) & Core wall Installation at Level +41.34 to Level +44.35 is in Progress.
• 29th of April 2009
Slab Form work at Level +44.35 (Level 18th, 11th Floor) & Core wall Installation at Level +41.34 to Level +44.35 is in Progress.
• 28th of April 2009
Slab Form work at Level +44.35 (Level 18th, 11th Floor) & Core wall Installation at Level +41.34 to Level +44.35 is in Progress.
• 27th of April 2009
Slab Form work at Level +44.35 (Level 18th, 11th Floor) is in Progress.
• 26th of April 2009
De shuttering of Vertical Elements Level 41.34 (Level 17th, 10th Floor) to 44.35 (Level 18th, 11th Floor).
• 23rd of April 2009
Concrete Casting of Vertical Elements Level 41.34 (Level 17th, 10th Floor) to 44.35 (Level 18th, 11th Floor).
•20th of April 2009
Concrete Casting of Slab Level at Level 41.34 (Level 17th, 10th Floor).
•12th of April 2009
Steel Fixing of Core wall at Level 41.34 is in Progress (Level 17th, 10th Floor).
• 9th of April 2009
Concrete Casting of Core wall Level 38.33 (Level 16th, 9th Floor) to 41.34 (Level 17th, 10th Floor).
• 1st of April 2009
Form work of Slab at Level 41.34 (Level 17th, 10th Floor).
• 28th of March 2009
Core wall Shuttering is in Progress.
• 22nd of March 2009
Concrete Casting of Vertical Elements Level 38.33 (Level 16th, 9th Floor) to 41.34 (Level 17th, 10th Floor).
• 19th of March 2009
Shuttering of Vertical Elements is in Progress.
• 18th of March 2009
Concrete Casting of Slab Level at Level 38.33 (Level 16th, 9th Floor).
• 15th of March 2009
Steel Fixing of Slab at Level 38.33 (16th) is in Progress.
• 10th of March 2009
Columns Installation Level 38.33 (16th) to 41.34 (17th) are Finished Today.
• 8th of March 2009
Steel Fixing at Level 38.33 (16th) is in Progress.
• 3rd of March 2009
Form work of Slab at Level 38.33 (16th) is in Progress.
• 26th of February 2009
Concrete Casting of Vertical Elements Between Level 35.32 (15th) to Level 38.33 (16th).
• 25th of February 2009
Shuttering of Vertical Elements Between Level 35.32 (15th) to Level 38.33 (16th).
• 23st of February 2009
Concrete Casting of Slab Level 35.32 (15th).
• 18th of February 2009
Steel Fixing of Slab Level 35.32 (15th) is in Progress.
• 17th of February 2009
Installation of Vertical Elements Between Level 35.32 (15th) to Level 38.33 (16th).
• 15th of February 2009
Form work of Slab Level 35.32 (15th) will be Completed Today.