Wind Tower I Progress Graph

Graph Legend

Steel Cut and Bend
Steel Prefabrication
Steel Installation
Concrete Casting
Block work and finishing
 

• Construction Updates

Important Events:
Concrete casting of level 29.05 has been completed.

Concrete casting of slab level 29.05.

Latest news from the construction site:

7th of January 2009
Concrete casting of level 29.05 has been completed. Formwork of vertical elements level 29.05 to level 32.01 is in progress. Formwork of slab level 32.01 is in progress.

3rd of January 2009
Steel Installation of level 29.05 is in near completion. Steel installation of non-core vertical elements level 29.05 to level 32.01 has been completed.

 
 
 