Latest news
from the construction site:
7th of January 2009
Concrete casting of vertical elements level 29.43 to level 32.44 has been completed. Steel
installation of non-core vertical elements level 32.44 to
level 35.45 is in progress. Formwork of slab level 35.45
is in progress.
3rd of January 2009
Concrete casting of level 29.43 has been completed. Steel
installation of non-core vertical elements level 29.43 to
level 32.44 has been completed. Formwork of slab level 32.44
is in progress. |