•14th of July 2010
Core wall installation from level 19 to level 20 installation ,fire fighting & alarm system testing & commisioning ,Block Work & MEP Workis in progress.
•13th of July 2010
Core wall installation from level 19 to level 20 installation ,fire fighting & alarm system testing & commisioning ,Block Work & MEP Workis in progress.
•12th of July 2010
Column & Core wall installation from level 19 to level 20 installation ,fire fighting & alarm system testing & commisioning ,Block Work & MEP Workis in progress.
•11th of July 2010
Column & Core wall installation from level 19 to level 20 installation ,fire fighting & alarm system testing & commisioning ,Block Work & MEP Workis in progress.
•8th of July 2010
Curing at level 19 (15th floor), Column & Core wall installation from level 19 to level 20 installation ,fire fighting & alarm system testing & commisioning ,Block Work & MEP Workis in progress.
•7th of July 2010
Curing at level 19 (15th floor), Column & Core wall installation from level 19 to level 20 installation ,fire fighting & alarm system testing & commisioning ,Block Work & MEP Workis in progress.
•6th of July 2010
Curing & postension work at level 19 (15th floor), Column & Core wall installation from level 19 to level 20 installation ,fire fighting & alarm system testing & commisioning ,Block Work & MEP Workis in progress.
•5th of July 2010
Curing at level 19 (15th floor),fire fighting & alarm system testing & commisioning ,Block Work & MEP Workis in progress.
•4th of July 2010
Curing at level 19 (15th floor),fire fighting & alarm system testing & commisioning ,Block Work & MEP Workis in progress.
•3rd of July 2010
Curing at level 19 (15th floor),fire fighting & alarm system testing & commisioning ,Block Work & MEP Workis in progress.
•2nd of July 2010
Curing at level 19 (15th floor),fire fighting & alarm system testing & commisioning ,Block Work & MEP Workis in progress.
1st of July 2010
Casting at level 19 (15th floor),fire fighting & alarm system testing & commisioning ,Block Work & MEP Workis in progress.
•3rd of June 2010
Top bar steel fixing & box fixining &MEP work at level 19 (15th floor),fire fighting & alarm system testing & commisioning ,Block Work & MEP Workis in progress.
•2nd of June 2010
Top bar steel fixing & box fixining &MEP work at level 19 (15th floor),fire fighting & alarm system testing & commisioning ,Block Work & MEP Work is in progress.
•1st of June 2010
Top bar steel fixing & box fixining MEP work at level 19 (15th floor),fire fighting & alarm system testing & commisioning ,Block Work & MEP Work is in progress.
•31th of May 2010
Top bar steel fixing & Postension work & MEP work at level 19 (15th floor),fire fighting & alarm system testing & commisioning ,Block Work & MEP Work is in progress.
•30th of May 2010
Top bar steel fixing & Postension work & MEP work at level 19 (15th floor),fire fighting & alarm system testing & commisioning ,Block Work & MEP Work is in progress.
•27th of May 2010
Top bar steel fixing & Postension work & MEP work at level 19 (15th floor),fire fighting & alarm system testing & commisioning ,Block Work & MEP Work is in progress.
•26th of May 2010
Top bar steel fixing & Postension work & MEP work at level 19 (15th floor),fire fighting & alarm system testing & commisioning ,Block Work & MEP Work is in progress.
•25th of May 2010
Postension work & MEP work at Level 19 (15th floor) ,Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•24th of May 2010
Postension work & MEP work at Level 19 (15th floor) ,Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•23th of May 2010
Postension work & MEP work at Level 19 (15th floor) ,Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•20th of May 2010
Postension work & MEP work at Level 19 (15th floor) ,Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•19th of May 2010
Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•18th of May 2010
Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•17th of May 2010
Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•16th of May 2010
Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•13th of May 2010
Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•12th of May 2010
Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•11th of May 2010
Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•10th of May 2010
Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•09th of May 2010
Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•06th of May2010
Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•05th of May 2010
Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•04th of May 2010
Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•03rd of May 2010
Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•02nd of May 2010
Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•29th of April 2010
Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•28th of April 2010
Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•27th of April 2010
Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•26th of April 2010
Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•25th of April 2010
Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•22th of April 2010
Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•21th of April 2010
Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•20th of April 2010
Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•19th of April 2010
Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•18th of April 2010
Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•15th of April 2010
Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•14th of April 2010
Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•13th of April 2010
Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•12th of April 2010
Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•11th of April 2010
Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•08th of April 2010
Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•07th of April 2010
Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•06th of April 2010
Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•05th of April 2010
Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•04th of April 2010
Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•01st of April 2010
Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•31th of March 2010
Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•30th of March 2010
Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•29th of March 2010
Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•28th of March 2010
Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•25th of March 2010
Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•24th of March 2010
Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•23th of March 2010
Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•22th of March 2010
Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•18th of March 2010
Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•17th of March 2010
Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•16th of March 2010
Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•15th of March 2010
Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•14th of March 2010
Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•11th of March 2010
Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•10th of March 2010
Fire fighting & alarm system installation , MEP work & Block work & retail work is in progress.
•09th of March 2010
Fire fighting & alarm system installation , MEP work & Block work is in progress.
•08th of March 2010
Fire fighting & alarm system installation , MEP work & Block work is in progress.
•07th of March 2010
Fire fighting & alarm system installation , MEP work & Block work is in progress.
•04th of March 2010
Fire fighting & alarm system installation , MEP work & Block work is in progress.
•03rd of March 2010
Fire fighting & alarm system installation , MEP work & Block work is in progress.
•02nd of March 2010
Fire fighting & alarm system installation , MEP work & Block work is in progress.
•01st of March 2010
Fire fighting & alarm system installation , MEP work & Block work is in progress.
•28th of February 2010
Fire fighting & alarm system installation , MEP work & Block work is in progress.
•25th of February 2010
Fire fighting & alarm system installation , MEP work & Block work & Core wall installation is in progress.
•24th of February 2010
Fire fighting & alarm system installation , MEP work & Block work is in progress.
•23th of February 2010
Fire fighting & alarm system installation , MEP work & Block work is in progress.
•22th of February 2010
Fire fighting & alarm system installation , MEP work & Block work is in progress.
•21th of February 2010
Fire fighting & alarm system installation , MEP work & Block work is in progress.
•18th of February 2010
Core Wall Installatoin 17th to 18th & MEP work & Block work is in progress.
•17th of February 2010
Core Wall Installatoin 17th to 18th & MEP work & Block work is in progress.
•16th of February 2010
Core Wall Installatoin 17th to 18th & MEP work & Block work is in progress.
•15th of February 2010
Core Wall Installatoin 17th to 18th & MEP work & Block work is in progress.
•14th of February 2010
Core Wall Installatoin 17th to 18th & MEP work & Block work is in progress.
•09th of February 2010
Core Wall Installatoin 17th to 18th & MEP work & Block work is in progress.
•08th of February 2010
Core Wall Installatoin 17th to 18th & MEP work & Block work is in progress.
•07th of February 2010
Staircase work 17th to 18th & MEP work & Block work is in progress.
•04th of February 2010
Staircase work 17th to 18th & MEP work & Block work is in progress.
•03rd of February 2010
Staircase work 17th to 18th & MEP work & Block work is in progress.
•02nd of February 2010
Core wall installation at levele 19th to 20th & staircase work 17th to 18th is in progress.
•01st of February 2010
Core wall prefabrication & installation at levele 19th to 20th & staircase work 17th to 18th is in progress.
•31st of January 2010
Core wall prefabrication & installation at levele 19th to 20th & staircase work 17th to 18th is in progress.
•28th of January 2010
Steel Fixing & MEP work at level 19th & Core wall prefabrication & installation at levele 19th to 20th & staircase work 17th to 18th is in progress.
•27th of January 2010
Steel Fixing & MEP work at level 19th & Core wall prefabrication & installation at levele 19th to 20th & staircase work 17th to 18th is in progress.
•26th of January 2010
Steel Fixing & MEP work at level 19th & Core wall prefabrication & installation at levele 19th to 20th & staircase work 17th to 18th is in progress.
•25th of January 2010
Steel Fixing & MEP work at level 19th & Core wall prefabrication & installation at levele 19th to 20th & staircase work 17th to 18th is in progress.
•24th of January 2010
Steel Fixing & MEP work at level 19th & Core wall prefabrication 19th to 20th & staircase work 17th to 18th is in progress & Fair Fighting pump has arrived to the wind site.
•21th of January 2010
Steel Fixing & MEP work at level 19th & Core wall prefabrication 19th to 20th & staircase work 17th to 18th is in progress.
•20th of January 2010
Steel Fixing & MEP work at level 19th & Core wall prefabrication 19th to 20th is in progress.
•19th of January 2010
Steel Fixing & MEP work at level 19th & Core wall prefabrication 19th to 20th is in progress.
•18th of January 2010
Steel Fixing & MEP work at level 19th & Core wall prefabrication 19th to 20th is in progress. Also today second part of Elevators and Equipments has arrived in the Wind sites which are been unloading right now
•17th of January 2010
Steel Fixing & MEP work is in progress. Also today Elevators and Equipments has arrived in the Wind sites which are been unloading right now
•14th of January 2010
Steel Fixing & MEP work is in progress.
•13th of January 2010
Beam Installation & MEP Work& Bottom Mesh steel Fixing is in progress.
•12th of January 2010
Beam Installation & MEP Work& Bottom Mesh steel Fixing is in progress.
•11th of January 2010
Beam Installation & MEP Work& Bottom Mesh steel Fixing is in progress.
•10th of January 2010
Beam Installation & MEP Work& Bottom Mesh steel Fixing is in progress.
•7th of January 2010
Beam Installation & MEP Work& Bottom Mesh steel Fixing is in progress.
•23th of December 2009
Slab Fixing At Level 19 & Bottom Mesh still Fixing in progress.
•22th of December 2009
Slab Fixing At Level 19 & Bottom Mesh still Fixing in progress.
•21th of December 2009
Slab Fixing At Level 19 & Towercain erection is in progress.
•20th of December 2009
Slab Fixing At Level 19 & Towercain erection is in progress.
•17th of December 2009
Slab Fixing At Level 19.
•15th of December 2009
Slab Fixing At Level 19.
•14th of December 2009
Slab Fixing At Level 19.
•12th of December 2009
core wall Shuttering from level 18 to level 19 & doka system slab removed from level 17 to level 19 is in progress & wind material is received.
•10th of December 2009
core wall Shuttering from level 18 to level 19 & doka system slab removed from level 17 to level 19 is in progress & wind material is received.
•9th of December 2009
core wall Shuttering from level 18 to level 19 & doka system slab removed from level 17 to level 19 is in progress.
•8th of December 2009
core wall Shuttering from level 18 to level 19 & doka system slab removed from level 17 to level 19 is in progress.
•7th of December 2009
core wall installation from level 18 to level 19 & doka system slab removed from level 17 to level 19 is in progress.
•6th of December 2009
Core wall steel fixing & table shifting at level 18th to 19th.
•3th of December 2009
column de shuttering & core wall installation & final stressing at level 18th to 19th.
•2nd of December 2009
column casting at 18th to level 19th.
•1st of December 2009
core wall installation from level 18th to level 19th & column shuttering is finished & ready to casting.
•30th of November 2009
core wall installation & curing & column shuttering dar level 18th.
•29th of November 2009
curing at level 18 & column fixing.
•26th of November 2009
Casting the slab of level 18th is finished.
•25th of November 2009
column installation at level 18 to level 19 & level 18 is ready to casting,casting will
be done at 9 o'clock.
•19th of November 2009
ssk & mep work & top bar steel fixing work at Level 18 is in Progress.
•18th of November 2009
Steel Fixing & MEP Work & SSK work at Level 18 is in Progress.
•15th of November 2009
ssk work & mep work at Level 18 is in Progress.
•12th of November 2009
ssk work & mep work at Level 18 is in Progress.
•11th of November 2009
ssk work & mep work at Level 18 is in Progress.
•10th of November 2009
ssk work & mep work at Level 18 is in Progress.
•8th of November 2009
steel fixing & mep work at Level 18 is in Progress.
•2nd of November 2009
Bottom Mesh Steel Fixing & Doka System Installation at Level 18 is in Progress.
•1st of November 2009
Bottom Mesh Steel Fixing at Level 18 is in Progress.
•29 th of October 2009
Doka System Installation at Level 18 & Core Wall De Shuttering at Level 17 to Level 18 is in Progress.
•28 th of October 2009
Doka System Installation at Level 18 is in Progress & Core Wall Casting at Level 17 to Level 18 is Finished.
•27 th of October 2009
Doka System Installation at Level 18 is in Progress & Core Wall Shuttering at Level 17 to Level 18 is Finished & Ready to Casting.
•26 th of October 2009
Doka System Installation at Level 18 & Core Wall Shuttering & Steel Fixing at Level 17 to Level 18 is in Progress.
•25 th of October 2009
Doka System Installation at Level 18 & Core Wall Shuttering & Steel Fixing at Level 17 to Level 18 is in Progress.
•21 th of October 2009
Column De Shuttering & Core Wall Steel Fixing done at Level 17 to Level 18 Is in Progress
•20 th of October 2009
Column De Shuttering & Core Wall Steel Fixing at Level 17 to Level 18 Is in Progress
•19 th of October 2009
Column De Shuttering & Core Wall Steel Fixing at Level 17 to Level 18 Is in Progress
•18 th of October 2009
Column De Shuttering & Core Wall Steel Fixing at Level 17 to Level 18 Is in Progress.
•17 th of October 2009
Casting Columns & Casting Stair Case
•15 th of October 2009
Column Shuttering at Level 17 to Level 18 Is in Progress.
•14 th of October 2009
Column Steel Fixing & Shuttering at Level 17 to Level 18 Is in Progress.
•13 th of October 2009
Column Steel Fixing at Level 17 to Level 18 Is in Progress.
•12 th of October 2009
Curing at Level 17 (+52.47) & Column Steel Fixing at Level 17 to Level 18 Is in Progress.
•11 th of October 2009
Casting & Curing at Level 17 (+52.47) & 8th Floor Block Work & Temporary Fire Fitting & Fire Alarm Is in Progress.
•08 th of October 2009
Cleaning at Level 17 (+52.47) & Ready to Casting & 8th Floor Block Work & Temporary Fire Fitting & Fire Alarm Is in Progress.
•07 th of October 2009
SSk Work & MEP Work & Cleaning at Level 17 (+52.47) & 8th Floor Block Work & Temporary Fire Fitting & Fire Alarm Is in Progress.
•06 th of October 2009
SSk Work & MEP Work & Top Bar Installation at Level 17 (+52.47) & 8th Floor Block Work & Temporary Fire rated Door Installation & Temporary Fire Fitting & Fire Alarm Is in Progress.
•04 th of October 2009
SSk Work & MEP Work & Top Bar Installation at Level 17 (+52.47) & 8th Floor Block Work & Temporary Fire rated Door Installation & Temporary Fire Fitting & Alarm Is in Progress.
•01 th of October 2009
SSk Work & MEP Work & Top Bar Installation at Level 17 (+52.47) & 8th Floor Block Work & Temporary Fire rated Door Installation Is in Progress.
•30 th of September 2009
Steel Fixing at Level 17 (+52.47) & 8th Floor Block Work & Temperary Fire rated Door Installation Is in Progress.
•29 th of September 2009
Steel Fixing at Level 17 (+52.47) & 8th Floor Block Work & Temporary Fire rated Door Installation Is in Progress.
•28 th of September 2009
Steel Fixing at Level 17 (+52.47) & 8th Floor Block Work & Temporary Fire rated Door Installation Is in Progress.
•27 th of September 2009
Steel Fixing at Level 17 (+52.47) & 8th Floor Block Work & Temporary Fire rated Door Installation Is in Progress.
•24 th of September 2009
Slab Fixing at Level 17 (+52.47) & 8th Floor Block Work & Temporary Fire rated Door Installation Is in Progress.
•23 th of September 2009
Slab Fixing at Level 17 (+52.47) & 8th Floor Block Work & Temporary Fire rated Door Installation Is in Progress.
•22 th of September 2009
Slab Fixing at Level 17 (+52.47) & 8th Floor Block Work & Temporary Fire rated Door Installation Is in Progress.
•19 th of September 2009
Slab Fixing at Level 17 (+52.47) & 8th Floor Block Work & Temporary Fire rated Door Installation Is in Progress.
• 28th of August 2009 Slab Removing from Level 14 to Level 16 (+41.47 to +47.49) & 7th Floor Block Work & Temporary Fire rated Door Installation Is in Progress.
• 27th of August 2009 Slab Removing from Level 14 to Level 16 (+41.47 to +47.49) & 7th Floor Block Work & Temporary Fire rated Door Installation Is in Progress.
• 23th of August 2009
Doka Bracket system installation at Level 16 (+47.49) & 7th Floor Block Work & Temporary Fire rated Door Installation Is in Progress.
• 20th of August 2009
Doka Bracket system installation at Level 16 (+47.49) & 7th Floor Block Work & Temporary Fire rated Door Installation Is in Progress.
• 19th of August 2009
Core Wall De Shuttering at Level 16 to Level 17 (+47.49 to 52.47)& 7th Floor Block Work & Temporary Fire rated Door Installation Is in Progress.
• 18th of August 2009
Core Wall Casting at Level 16 to Level 17 (+47.49 to 52.47) & Curing at Level 16 & 7th Floor Block Work & Temporary Fire rated Door Installation Is in Progress.
• 17th of August 2009
Core Wall Shuttering at Level 16 to Level 17 (+47.49 to 52.47) & Curing at Level 16 & 6th Floor Block Work & Temporary Fire rated Door Installation Is in Progress.
• 16th of August 2009
Core Wall Shuttering at Level 16 to Level 17 (+47.49 to 52.47) & Curing at Level 16 & 6th Floor Block Work & Temporary Fire rated Door Installation Is in Progress.
• 13th of August 2009
Column De Shuttering at Level 16 to Level 17 (+47.49 to 52.47) & Core Wall Shuttering at Level 16 to Level 17 (+47.49 to 52.47) & Curing at Level 16 & 6th Floor Block Work & Temporary Fire rated Door Installation Is in Progress.
• 12th of August 2009
Column De Shuttering at Level 16 to Level 17 (+47.49 to 52.47) & Core Wall Shuttering at Level 16 to Level 17 (+47.49 to 52.47) & Curing at Level 16 & 6th Floor Block Work & Temporary Fire rated Door Installation Is in Progress.
• 11th of August 2009
Column De Shuttering at Level 16 to Level 17 (+47.49 to 52.47) & Core Wall Shuttering at Level 16 to Level 17 (+47.49 to 52.47) & Curing at Level 16 & 6th Floor Block Work & Temporary Fire rated Door Installation Is in Progress.
• 10th of August 2009
Column Shuttering at Level 16 to Level 17 (+47.49 to 52.47) & Curing at Level 16 & 6th Floor Block Work & Temporary Fire rated Door Installation Is in Progress & Column Is Ready to Casting.
• 09th of August 2009
Column Shuttering at Level 16 to Level 17 (+47.49 to 52.47) & Curing at Level 16 & 6th Floor Block Work & Temporary Fire rated Door Installation Is in Progress.
• 06th of August 2009
Column Shuttering at Level 16 to Level 17 (+47.49 to 52.47) & Curing at Level 16 & 6th Floor Block Work & Temporary Fire rated Door Installation Is in Progress.
• 05th of August 2009
Casting & Curing at Level 16 (+47.49) & 6th Floor Block Work & Temporary Fire rated Door Installation Is in Progress.
• 04th of August 2009
Core Wall Installation at Level 16 to Level 17 (+47.49 to 52.47) & 6th Floor Block Work & Temporary Fire rated Door Installation Is in Progress & Slab Ready to Casting.
• 03rd of August 2009
Top Mesh Steel Fixing & MEP work at Level 16 (+47.49) & 6th Floor Block Work & Core Wall Installation at Level 16 to Level 17 (+47.49 to 52.47) & Temporary Fire rated Door Installation Is in Progress.
• 02nd of August 2009
Top Mesh Steel Fixing & MEP work at Level 16 (+47.49) & 6th Floor Block Work & Column Installation at Level 16 to Level 17 (+47.49 to 52.47) & Temporary Fire rated Door Installation Is in Progress.
• 30th of July 2009
Top Mesh Steel Fixing & MEP work at Level 16 (+47.49) & 6th Floor Block Work & Column Installation at Level 16 to Level 17 (+47.49 to 52.47) & Transfer Beam Shuttering & Temporary Fire rated Door Installation Is in Progress.
• 29th of July 2009
Bottom Mesh Steel Fixing & MEP work at Level 16 (+47.49) & 6th Floor Block Work & Column Installation at Level 16 to Level 17 (+47.49 to 52.47) & Transfer Beam Installation & Temporary Fire rated Door Installation Is in Progress.
• 28th of July 2009
Bottom Mesh Steel Fixing at Level 16 (+47.49) & 6th Floor Block Work & Column Installation at Level 16 to Level 17 (+47.49 to 52.47) & Temporary Fire rated Door Installation Is in Progress.
• 27th of July 2009
Bottom Mesh Steel Fixing at Level 16 (+47.49) & 6th Floor Block Work &Temporary Fire rated Door Installation Is in Progress.
• 26th of July 2009
Slab Fixing at Level 16 (+47.49) & Beam Steel Fixing at Level 16 (+47.49) & 6th Floor Block Work &Temporary Fire rated Door Installation Is in Progress.
• 23th of July 2009
Slab Fixing at Level 16 (+47.49) & Beam Steel Fixing at Level 16 (+47.49) & 6th Floor Block Work &Temporary Fire rated Door Installation Is in Progress.
• 22th of July 2009
Slab Fixing at Level 16 (+47.49) & Base of Column Casting & 6th Floor Block Work &Temporary Fire rated Door Installation Is in Progress.
• 21th of July 2009
Slab Fixing at Level 16 (+47.49) & 6th Floor Block Work & Temporary Fire rated Door Installation Is in Progress.
• 20th of July 2009
Slab Fixing at Level 16 (+47.49) & 6th Floor Block Work & Temporary Fire rated Door Installation Is in Progress.
• 16th of July 2009
Slab Fixing at Level 16 (+47.49) & Temporary Fire rated Door Installation Is in Progress.
• 15th of July 2009
Slab Fixing at Level 16 (+47.49) & Temporary Fire rated Door Installation Is in Progress.
• 14th of July 2009
Slab Fixing at Level 16 (+47.49) & Temporary Fire rated Door Installation Is in Progress.
• 13th of July 2009
Slab Fixing at Level 16 (+47.49) & Temporary Fire rated Door Installation Is in Progress.
• 12th of July 2009
Slab Fixing at Level 16 (+47.49) & Temporary Fire rated Door Installation Is in Progress.
• 09th of July 2009
Slab Fixing at Level 16 (+47.49) & Temporary Fire rated Door Installation Is in Progress.
• 08th of July 2009
Slab Fixing at Level 16 (+47.49) & Temporary Fire rated Door Installation Is in Progress.
• 07th of July 2009
Slab Fixing at Level 16 (+47.49) & Temporary Fire rated Door Installation Is in Progress.
• 06th of July 2009
Slab Fixing at Level 16 (+47.49) & Temporary Fire rated Door Installation Is in Progress.
• 05th of July 2009
Slab Fixing at Level 16 (+47.49) & Temporary Fire rated Door Installation Is in Progress.
• 02nd of July 2009
Slab Fixing at Level 16 (+47.49) & Temporary Fire rated Door Installation & Transfer Beam De Shuttering Is in Progress.
• 01st of July 2009
Slab Fixing at Level 16 (+47.49) & Temporary Fire rated Door Installation & Transfer Beam Casting Is in Progress.
• 30th of June 2009
Slab Fixing at Level 16 (+47.49) & Temporary Fire rated Door Installation & Transfer Beam Shuttering Is in Progress.
• 29th of June 2009
Slab Fixing at Level 16 (+47.49) & Temporary Fire rated Door Installation & Transfer Beam Shuttering Is in Progress.
• 28th of June 2009
Slab Fixing at Level 16 (+47.49) & Temporary Fire rated Door Installation & Transfer Beam Shuttering Is in Progress.
• 25th of June 2009
Slab Fixing at Level 16 (+47.49) & Temporary Fire rated Door Installation & Transfer Beam Shuttering Is in Progress.
• 24th of June 2009
Slab Fixing at Level 16 (+47.49) & Temporary Fire rated Door Installation & Transfer Beam Shuttering Is in Progress.
• 23th of June 2009
Slab Fixing at Level 16 (+47.49) & Temporary Fire rated Door Installation & Transfer Beam Shuttering Is in Progress.
• 22th of June 2009
Slab Fixing at Level 16 (+47.49) & Temporary Fire rated Door Installation & Transfer Beam Shuttering Is in Progress.
• 21th of June 2009
Slab Removing at Level 14 to Level 16 (+41.47 to +47.49) & Temporary Fire rated Door Installation & Transfer Beam Shuttering Is in Progress.
• 18th of June 2009
Slab Removing at Level 14 to Level 16 (+41.47 to +47.49) & Temporary Fire rated Door Installation & Transfer Beam Shuttering Is in Progress.
• 17th of June 2009
Slab Removing at Level 14 to Level 16 (+41.47 to +47.49) & Temporary Fire rated Door Installation & Transfer Beam Installation Is in Progress.
• 16th of June 2009
Slab Removing at Level 14 to Level 16 (+41.47 to +47.49) & Temporary Fire rated Door Installation & Transfer Beam Installation Is in Progress.
• 15th of June 2009
Slab Removing at Level 14 to Level 16 (+41.47 to +47.49) & Temporary Fire rated Door Installation & Core wall De Shuttering at Level 15 to Level 16 (+44.48 to +47.49) & Transfer Beam Installation Is in Progress.
• 14th of June 2009
Slab Removing at Level 14 to Level 16 (+41.47 to +47.49) & Temporary Fire rated Door Installation Is in Progress & Core wall Shuttering at Level 15 to Level 16 (+44.48 to +47.49) Is Finished & Ready to Casting.
• 11th of June 2009
Slab Removing at Level 14 to Level 16 (+41.47 to +47.49) & Core wall Shuttering at Level 15 to Level 16 (+44.48 to +47.49) & Temporary Fire rated Door Installation Is in Progress.
• 10th of June 2009
Slab Removing at Level 14 to Level 16 (+41.47 to +47.49) & Core wall Shuttering at Level 15 to Level 16 (+44.48 to +47.49) & Temporary Fire rated Door Installation Is in Progress.
• 09th of June 2009
Column De Shuttering at Level 15 to Level 16 (+44.48 to +47.49) & Core wall Shuttering at Level 15 to Level 16 (+44.48 to +47.49) & Temporary Fire rated Door Installation Is in Progress.
• 08th of June 2009
Column De Shuttering at Level 15 to Level 16 (+44.48 to +47.49) & Core wall Installation & Shuttering at Level 15 to Level 16 (+44.48 to +47.49) Is In Progress & Curing at Level 15 (11th floor +44.48) & Temporary Fire rated Door Installation Is in Progress.
• 07th of June 2009
Column De Shuttering at Level 15 to Level 16 (+44.48 to +47.49) & Core wall Shuttering at Level 15 to Level 16 (+44.48 to +47.49) Is In Progress & Curing at Level 15 (11th floor +44.48) & Temporary Fire rated Door Installation Is in Progress
• 04th of June 2009
Column Installation & Shuttering at Level 15 to Level 16 (+44.48 to +47.49) Is In Progress & Curing at Level 15 (11th floor +44.48) Is in Progress
• 03rd of June 2009
Casting of Slab at Level 44.48 (15th, 11th Floor).
• 02nd of June 2009
Transfer Beam Installation at Level 15 (11th floor +44.48) Is Finished & Cleaning at Level 15 (11th floor +44.48) Is in Progress & Slab Ready to The Casting
• 01st of June 2009
Transfer Beam Installation at Level 15 (11th floor +44.48) & 5th Floor Block Work Is in Progress.
• 31th of May 2009
Transfer Beam Installation at Level 15 (11th floor +44.48) & 5th Floor Block Work Is in Progress
• 28th of May 2009
Transfer Beam Installation at Level 15 (11th floor +44.48) & 5th Floor Block Work Is in Progress.
• 27th of May 2009
Column Installation at Level 15 to 16 (+44.48 to +47.49) & Steel Fixing at Level 15 (11th floor +44.48) & MEP Work at Level 15 (11th floor +44.48) & 5th Floor Block Work Is in Progress.
• 26th of May 2009
Steel Fixing at Level 15 (11th floor +44.48) & MEP Work at Level 15 (11th floor +44.48) & 5th Floor Block Work Is in Progress.
• 25th of May 2009
Column Installation at Level 15 to 16 (+44.48 to +47.49) & Steel Fixing at Level 15 (11th floor +44.48) & MEP Work at Level 15 (11th floor +44.48) & 5th Floor Block Work Is in Progress.
• 24th of May 2009
Column Installation at Level 15 to 16 (+44.48 to +47.49) & Steel Fixing at Level 15 (11th floor +44.48) & MEP Work at Level 15 (11th floor +44.48) & 5th Floor Block Work Is in Progress.
• 21th of May 2009
Column Installation at Level 15 to 16 (+44.48 to +47.49) & Slab Form work at Level 15 (11th floor +44.48) & Bottom Steel Fixing at Level 15 (11th floor +44.48) & 5th Floor Block Work is in progress.
• 20th of May 2009
Column Installation at Level 15 to 16 (+44.48 to +47.49) & Slab Form work at Level 15 (11th floor +44.48) & Bottom Steel Fixing at Level 15 (11th floor +44.48) & 5th Floor Block Work is in progress.
• 19th of May 2009
Column Installation at Level 15 to 16 (+44.48 to +47.49) & Slab Form work at Level 15 (11th floor +44.48) & 5th Floor Block Work is in progress.
• 18th of May 2009
Column Installation at Level 15 to 16 (+44.48 to +47.49) & Slab Form work at Level 15 (11th floor +44.48) & 4th Floor Block Work is in progress.
• 17th of May 2009
Column Installation at Level 15 to 16 (+44.48 to +47.49) & Slab Form work at Level 15 (11th floor +44.48) & 4th Floor Block Work is in progress.
• 14th of May 2009
Core wall De Shuttering at Level 14 to 15 (+41.47 to +44.48) & Slab Form work at Level 15 (11th floor +44.48) & 4th Floor Block Work is in progress.
• 13th of May 2009
Core wall De Shuttering at Level 14 to 15 (+41.47 to +44.48) & Slab Form work at Level 15 (11th floor +44.48) & 4th Floor Block Work is in progress.
• 12th of May 2009
Core wall Shuttering at Level 14 to 15 (+41.47 to +44.48) & Slab Form work at Level 15 (11th floor +44.48) & 4th Floor Block Work is in progress.
• 11th of May 2009
Core wall Shuttering at Level 14 to 15 (+41.47 to +44.48) & Slab Form work at Level 15 (11th floor +44.48) & 4th Floor Block Work is in progress.
• 10th of May 2009
Core wall Shuttering at Level 14 to 15 (+41.47 to +44.48) & Slab Form work at Level 15 (11th floor +44.48) & 4th Floor Block Work is in progress.
• 07th of May 2009
Core wall Shuttering at Level 14 to 15 (+41.47 to +44.48) & Slab Form work at Level 15 (11th floor +44.48) & 4th Floor Block Work is in progress.
• 06th of May 2009
Core wall Installation Level 14 to 15 (+41.47 to +44.48) & +41.47) & Slab Form Work at Level 15 & 4th Floor Block Work is in progress.
• 05th of May 2009
Core wall Installation Level 14 to 15 (+41.47 to +44.48) & +41.47) & Slab Form Work at Level 15 & 4th Floor Block Work is in progress.
• 04th of May 2009
Core wall Installation Level 14 to 15 (+41.47 to +44.48) & +41.47) & Slab Form Work at Level 15 & 4th Floor Block Work is in progress.
• 03rd of May 2009
Core wall Installation Level 14 to 15 (+41.47 to +44.48) & Curing Slab Level 14 (10th floor +41.47) & 4th Floor Block Work is in progress.
• 30th of April 2009
4th floor block work is in progress.
• 30th of April 2009
Column Casting at Level 41.47 to Level 44.48 & Transfer Beam Installation at Level 44.48 & 4th floor block work is in progress.
• 29th of April 2009
Column installation & Shuttering at Level 41.47 to Level 44.48 & 4th floor block work is in progress.
• 28th of April 2009
Column installation at Level 41.47 to Level 44.48 is in progress.
• 27th of April 2009
Curing of Slab at Level 41.47 (14th, 10th Floor).
• 26th of April 2009
Casting of Slab at Level 41.47 (14th, 10th Floor).
• 23rd of April 2009
Installation of Vertical Elements, Level 41.47 to Level 44.48 is in Progress & Block work at Third Level is Finished.
• 19th of April 2009
Steel Fixing & MEP Work is in Progress at Level 41.47 (14th, 10th Floor).
• 13th of April 2009
Form work of Slab Level 41.47 (14th, 10th Floor) is in Progress.
• 12th of April 2009
Block Work at Third Level is Starting.
• 9th of April 2009
Concrete Casting of Core wall, Level 38.46 (13th, 9th Floor) to Level 41.47 (14th, 10th Floor).
• 1st of April 2009
Block Work at Second Level is in Progress.
• 28th of March 2009
Core wall Shuttering is in Progress.
• 18th of March 2009
Concrete Casting of Vertical Elements, Level 38.46 (13th, 9th Floor) to Level 41.47 (14th, 10th Floor).
• 16th of March 2009
Shuttering of Vertical Elements, Level 38.46 to Level 41.47 is in Progress.
• 12th of March 2009
Concrete Casting of Slab at Level 38.46 (13rd, 9th Floor).
• 10th of March 2009
Steel Fixing, MEP Work & Columns Installation at Level 38.46 (13th) are Finished.
• 5th of March 2009
Concrete Casting of Core wall Level 35.45 (12th) to Level 38.46 (13th).
• 3rd of March 2009
Steel Fixing & MEP Work of Slab at Level 38.46 (13th) is in Progress.
• 28th of February 2009
Block Work at First Level is in Progress.
• 25th of February 2009
Form work of Slab Level 38.46 (13th).
• 21st of February 2009
Concrete Casting of Vertical Elements Between Level 35.45 (12th) to Level 38.46 (13th).
•18th of February 2009
Curing of Slab, Level 35.45 (12th) is in Progress.
• 16th of February 2009
Concrete Casting of Slab, Level 35.45 (12th).
• 14st of February 2009
Steel Fixing of Level 35.45 (12th) is in Progress.